Construction Schedule*

Activity

Start

Finish

Site Clearing September, 2017 March, 2018
Access Roads to Turbine Site November, 2017 November, 2018
Turbine Foundations  April, 2018 January, 2019
Operations & Maintenance  Facility  June, 2018 July, 2019
Substation & Switchyard June, 2018 March, 2019
Turbine Deliveries July, 2018 February, 2019
Turbine Installation  July, 2018 April, 2019
Underground Collection  August, 2018 February, 2019
Land Restoration October, 2018 August, 2019