Construction Activities

Since our last update, our team has been working hard to put finishing touches on the project as we near the completion of construction at the Henvey Inlet Wind site. Currently, we continue to conduct safety inspections, ongoing environmental work and site restoration on the project site.  Work completed to date includes:

• 87 of 87 turbines have now been erected complete with 261 blades total;
• 100% of the cable has been installed and pulled into 87 turbines;
• 100% of the 104 km transmission line is now complete; and
• 100% of the North and South Substations are now complete.

To see the full project area, please visit our Site Map page.

Sign up here to receive construction updates through our e-newsletter.

Latest e-Newsletters

Construction Update - June 19, 2019

Construction Update - March 7, 2019 

Construction Update - February 4, 2019

Construction Update - January 15, 2018

Construction Update - December 24, 2018

Construction Update - December 11, 2018

Construction Update - November 6, 2018

Construction Update - October 15,2018 

Construction Update - September, 27 2018

Construction Update - September, 12 2018

Construction Update - August, 27 2018